The project management work was carried out as part of the conversion of the Torrevaldaliga Nord Thermal Power Plant into a coal-fired power plant in the Port of Civitavecchia.
The work specifically involved:
- First and second phase dredging;
- Construction of cellular caissons for the coal dock;
- Ballasting and backfilling of the main dock caissons;
- Foundation piles for the continuous loader pylon; Storage of dredged sediments at the “LA MATTONARA” storage site.
Services Carried Out:
Site Supervision
Site Supervisor:
Eng. Michelangelo Lentini
Amount of works:
$54,545,000.00
Service Period:
March 2007 - Jan 2010