Abu Qir Marine Port Container Terminal
The engineering services are related to the development of the Container Terminal at Abu Qir’s Marine Port.
The project includes:
A new container terminal with a 1.2 km quay with a lateral depth of -18 mCD and about 60 hectares of storage area;
Access channel and navigation area at level -17.6 mCD and a turning basin of 700 m in diameter, also at level -17.6 mCD; Breakwaters;
The works included in the construction contract are:
- Marine works: demolition and disposal of existing marine structures;
- quay structures; various facilities, including electrical, water bunkering, etc., and other quay fittings; dredging to be carried out for: new quay, access channel, turning basin, breakwaters;
- reclamation area next to the quay and soil treatment;
- new breakwaters.
Land works: removal and disposal of any hazardous materials; demolition of existing structures; paving of the access road with road signs; new entry and exit gates with portals and structures; structures for the container yard; internal roadways and connections to the existing road system; accessory works including drainage, HV and LV power supply and distribution, cabling and communication towers, water supply system, lighting installation; electrical substations; surveillance, control, and data acquisition system (SCADA); fire protection structures; RTGC maintenance workshop and platform; fuel system; drainage; improvement of existing public utilities and road connections, and provision of a new parking lot and maneuvering area for buses; underground ducts and chambers for electric RTGCs.